Project Description

The project objective was to restore critical lengths of deteriorated channel banks along the Gulf Intracoastal Waterway (GIWW) in Terrebonne Parish and stabilize/armor selected critical lengths of deteriorated channel banks with hard shoreline stabilization materials. A portion of this project was constructed using CIAP 2007 funds and the remainder of the project received Phase 2 funding through CWPPRA.

Issue Addressed

N/A

Project Goals

N/A

Verify Date

1/15/2020
Search for More Documents
  • No documents to display
  • No documents to display
  • No documents to display
  • No documents to display
  • No documents to display
  • No documents to display
  • No documents to display

Project Information

Project Type(s):

Shoreline Protection

Project ID:

TE-0043-EB

Basin(s):

Terrebonne

CPRA Program:

Coastal Impact Assistance Program (CIAP)

Federal Sponsor:

U.S. Fish and Wildlife Service (USFWS)

CPRA Project Phase:

Completed

Parish(es):

Terrebonne

Estimated Cost:

$ 7.3 million

Project Benefits

Restoration Icon
Acres Benefit:
  • 1180 acres benefited