Davis Pond Upper Barataria Risk Reduction


projectMap





Project Location

N/A

Project Description

This project consists of raising approximately two miles of the Davis Pond Diversion West Guide Levee to a uniform elevation of +7.5 ft NAVD88, constructing a T-Wall at the existing pipeline crossing, and conversion of the existing Tidal Exchange Structure to a permanent T-Wall.

Issue Addressed

N/A

Project Goals

N/A

Verify Date

1/26/2021
Search for More Documents
  • No documents to display
  • No documents to display
  • No documents to display
  • No documents to display
  • No documents to display
  • No documents to display
  • No documents to display
  • No documents to display

Project Information

Project Type(s):

Hurricane Protection

Project ID:

BA-0219

Basin(s):

Barataria

CPRA Program:

Gulf of Mexico Energy Security Act (GOMESA)

Federal Sponsor:

Bureau of Ocean Energy Management (BOEM)

CPRA Project Phase:

Headed to Bid

Parish(es):

Jefferson, St Charles

Estimated Cost:

$ 6.5 million

Project Benefits

Protection Icon
Miles of Levee Improved:
  • 2 miles of levee improved